Overview

Under the contract of KAR Group, we sandblasted 30 refinery tanks in Iraq, Erbil, to SA 2.5 norm. We applied 80 micron primer and 80 micron intermediate coat.

Paint thickness is quite important in hot climates.

Epoxy primer and acrylic paint type are quite resistant to UV rays.

We applied 100 micron white acrylic paint as the final coat.

Project Name

Erbil Refinery Tanks

Client

KAR Group

Project Start Date

09.01.2012

Project Completion Date

17.02.2012

Project Implementation Details

Under the contract of KAR Group, we sandblasted 30 refinery tanks in Iraq, Erbil, in accordance with SA 2.5 norm. We applied 80 micron primer and 80 micron intermediate coat. Paint thickness is quite important in hot climates. Epoxy primer and acrylic paint type are quite resistant to UV rays. We applied 100 micron white acrylic paint as the final coat.