Overview

While Şişecam Eskişehir factory was in the construction phase, we sandblasted the steel structures at SA 2.5 degrees.

We applied 80 micron primer and 70 micron intermediate coat.

As for the final coat, we applied 80 – 100 micron painting, with different parts, the general body white, the components yellow – gray.

Project Name

Şişecam Factory

Client

Şişecam

Project Start Date

17.08.2008

Project Completion Date

13.10.2008

Project Implementation Details

While Şişecam Eskişehir factory was under construction, we sandblasted the steel structures at SA 2.5 degrees.